Construction Project Updates

08/30/2024

****UPDATED****

UNDER CONSTRUCTION

Thank you for your patience.

ODOT- Wales Road Widening Project (STA SR241-9.71): IN PROGRESS, EXPECTED COMPLETION FALL 2024.
ODOT project award. Widening from Lincoln Way to the north. Seeding and top-soiling and final striping to be completed.
Contractor: Shelly Company, Thornville, Ohio

ODOT - US62/SR21 PID 94136 Microsurfacing Project: IN PROGRESS, SUMMER 2024, EXPECTED COMPLETION JUNE 2025.
ODOT project award. Resurfacing SR21/US62 from US30 south to Navarre Corporation limits.
Contractor: Strawser Construction, Columbus, Ohio

2022 Charles Ave SE Improvement Project: COMPLETED.
Contractor:
Lockhart Concrete Co., Akron, Ohio

2022 Erie Street South Improvement Project STA241 8.33 PID116456: COMPLETED.
Contractor: Shelly Company, Thornville, Ohio

2023 Lake Ave and Amherst Intersection Improvement: IN PROGRESS.
Contractor: Shelly Company, Thornville, Ohio

2023 8th St SW Sanitary Sewer and waterline Replacement Project: COMPLETED.
Contractor: RBS General Contracting, Massillon, Ohio

2024 Massillon Catch Basin Replacement Project: IN PROGRESS.
Contractor:
Holderbaum Sewer and Drain Service, Massillon, Ohio

2024 St Andrews Estates Roadway Improvement Project: COMPLETED.
Contractor: Albatross Management, Lakeville, Ohio

2024 Castlewest Estates Roadway Improvement Project: AUGUST 2024 START.
Contractor: Northstar Asphalt, N. Canton, Ohio

2024 ODOT 643 Pavement Marking City Streets Project: COMPLETED.
Contractor: Aero-Mark, Streetsboro, Ohio

2024 Wampler Park Pickleball Courts Project: IN PROGRESS.
Contractor: Lantzer & Sons, Asphalt and Concrete, Navarre, Ohio

2024 Wampler Splash Park Project: IN PROGRESS.
Contractor: DA Terreri, Youngstown, Ohio

2024 Levee Storm Water Valve Automation Project: IN PROGRESS.
Contractor: Stanley Miller Construction, East Sparta, Ohio

2024 Massillon Municipal Building HVAC Project: IN PROGRESS
Contractor: Standard Plumbing & Heating, Canton, Ohio

2024 Street Resurfacing Project: IN PROGRESS
Contractor: Superior Paving and Materials, N. Canton, Ohio

2024 MRF Hills and Dales Rd Resurfacing Project: IN PROGRESS
Contractor: Superior Paving and Materials, N. Canton, Ohio

Massillon Fire Department Building Addition Project:  IN PROGRESS
Contractor:
CCI, Commercial Construction, Canton, Ohio- General
Contractor:
Alpine Heating Ltd, Dundee, Ohio- HVAC
Contractor:
Wood Electric, New Philadelphia, Ohio - Electrical
Contractor:
Cline Mechanical Inc., Wadsworth, Ohio - Plumbing

UNDER DESIGN

2022 North Erie Canal/Burton Ave Storm Sewer Improvement Project: QBS, design COMPLETE
Consultant: Richland Engineering, Mansfield, Ohio

2022 20th St SE Area Storm Sewer Improvement Project: QBS, design COMPLETE
Consultant: OHM Advisors, Akron, Ohio

2022 26th St NW Area Storm Sewer Improvement Project: QBS, design COMPLETE
Consultant: OHM Advisors, Akron, Ohio

2024 Lincoln Way East Improvement- 1st NE to Wales Rd Improvement Project: IN PROGRESS
Designer:
City of Massillon

2024 Main Ave W Tremont SW Round About Project: IN PROGRESS
Designer: City of Massillon, Peer Review:  

 UPCOMING PROJECTS:
See our Forecasted Projects page

Dates and Times are subject to changes.

Construction Notes:

The Engineering Department develops plans and specifications and provides construction management services for sanitary and storm sewers, storm water and water quality management systems, and roadway improvements. We also assist other City departments with design services for maintenance and improvements to various facilities.

Roadway improvement projects are identified either through the City’s five-year capital improvement program, or the Stark County Area Transportation Study program. Storm drainage improvements are also done in accordance with the City’s capital improvement program and on an as needed basis.

Construction Inspection/Administration includes the inspection of various projects that include sanitary sewer, storm drainage, roadway reconstruction and resurfacing projects under contract by the City of Massillon.