06/01/2026
****UPDATED****
UNDER CONSTRUCTION
Thank you for your patience.
Levee Storm Water Valve Automation Project: IN PROGRESS.
Contractor: Stanley Miller Construction, East Sparta, Ohio
Construction Admin: Municipal Services Group, Massillon, Ohio
North Erie Canal/Burton Ave Storm Sewer Improvement Project: NEARING COMPLETION.
Contractor: Lockhart Concrete, Akron, Ohio
CA/Inspection: OHM Advisors, Akron, Ohio
Waterline Replacement: AQUA Ohio
Lincoln Way 1st NW to 1st SW Intersection Improvement: NEARING COMPLETION.
Contractor: Shelly Company, Thornville, Ohio
CA/Inspection: City of Massillon
Sanitary Sewer Improvement Project: NEARING COMPLETION.
Contractor: Cavanaugh Building, Akron, Ohio
CA/Inspection: City of Massillon
Millennium Blvd SE Lighting Project: IN PROGRESS, Summer start.
Contractor: Bachtel Excavating, Massillon, Ohio
CA/Inspection: Municipal Services Group, Massillon, Ohio
Federal Ave Pump Station Storm Water Gate Replacement Project: IN PROGRESS, awaiting delivery.
Contractor: Stanley Miller Construction, East Sparta, Ohio
Construction Admin: City of Massillon
Springhill Settlement Improvement Project Phase V: IN PROGRESS, July start.
Contractor: Northstar Asphalt, N. Canton, Ohio
CA/Inspection: City of Massillon
Reservoir Park Streambank Restoration Project: NEARING COMPLETION.
Contractor: Marks Construction, Valley City, Ohio
CA/Inspection: Municipal Services Group, Massillon, Ohio
2026 Street Resurfacing Project: IN PROGRESS, catch basins and curb ramp installation.
Contractor: Superior Paving and Materials, N. Canton, Ohio
CA/Inspection: City of Massillon
Recreation Center Parking Lot Resurfacing Project: IN PROGRESS.
Contractor: Northstar Asphalt, N. Canton, Ohio
CA/Inspection: City of Massillon
Main Ave and Tremont SW Roundabout Project: IN PROGRESS.
Contractor: S.E.T., Lowellville, Ohio
CA/Inspection: EDG, Akron, Ohio
UNDER DESIGN
Warmington Road SW Widening Project: DESIGN COMPLETED, FALL BID
Designer: City of Massillon
Lincoln Way East Improvement- 1st NE to Wales Rd Improvement Project: DESIGN IN PROGRESS
Designer: City of Massillon
ODOT STA21-10.46 SR21 LAKE AVE CORRIDOR Project- DESIGN IN PROGRESS
Designer: American StructurePoint, Akron, Ohio
PUBLIC INVOLVEMENT
Massillon Reservoir Park Revitalization Project Phase II: DESIGN IN PROGRESS
Designer: EDG, Akron, Ohio
UPCOMING PROJECTS:
See our Forecasted Projects page
Dates and Times are subject to changes.
Construction Notes:
The Engineering Department develops plans and specifications and provides construction management services for sanitary and storm sewers, storm water and water quality management systems, and roadway improvements. We also assist other City departments with design services for maintenance and improvements to various facilities.
Roadway improvement projects are identified either through the City’s five-year capital improvement program, or the Stark County Area Transportation Study program. Storm drainage improvements are also done in accordance with the City’s capital improvement program and on an as needed basis.
Construction Inspection/Administration includes the inspection of various projects that include sanitary sewer, storm drainage, roadway reconstruction and resurfacing projects under contract by the City of Massillon.